Q & A

設計費點計?

How is your interior design fee calculated?

設計費按面積、設計要求計算。

住宅按平方呎報價;商業及酒店項目按階段報價——概念、深化設計、施工圖、FF&E 規格。

首次會面及初步平面建議免費,正式報價在設計圖批後提供。

Design fees are based on floor area, scope and revision rounds. Residential projects are quoted per square foot; commercial and hotel projects are quoted by stage — concept, design development, construction drawings and FF&E specification. The first meeting and initial floor-plan advice are free; a formal quotation follows an Design approval.

由第一次傾到入伙要幾耐?

How long from first meeting to move-in?

首次會面及平面建議 1–2 星期;度尺及 3D 設計 2–4 星期;工程 6–12 星期,視乎面積及工程範圍。住宅項目合共約 2–5 個月,商業項目按面積及機電要求另議。

Allow 1–2 weeks for the first meeting and floor-plan options, 2–4 weeks for measuring and 3D design, and 6–12 weeks for construction depending on size and scope. Residential projects typically take 2–5 months in total; commercial programmes are agreed case by case around M&E requirements.

點樣開始?第一次要準備咩資料?

How do I get started, and what should I prepare?

準備三樣就可以:單位地址及面積、你想改善的地方(可附參考圖片)、預算範圍及期望入伙時間。然後 WhatsApp 或致電 +852 52011341 預約首次會面,首次會面及初步平面建議免費。

​

Three things: the address and floor area, what you want to improve (reference images welcome), and your budget range plus target move-in date. Then call or WhatsApp +852 3590 5902 to book a first meeting — the first meeting and initial floor-plan advice are free.

報價包唔包傢俬同物料?

Does the quotation include furniture and materials?

報價分兩部分:工程價(泥水、木工、油漆、水電、五金)及傢俬物料價。可獨立報價。你可選擇全部交由我們承造,或只做固定裝修,活動傢俬自行採購。

Quotations are split in two: construction works (masonry, carpentry, painting, plumbing and electrical, hardware) and furniture/materials. Bespoke furniture is produced in our own Zhuhai factory and can be quoted separately. You may hand us the full scope, or take fixed works only and source loose furniture yourself.

你哋嘅流程係點?

What is your design and renovation process?

五步:(00) 你提供單位基本資料 → (01) 首次會面並提供平面建議 → (02) 上門專業度尺 → (03) 3D 設計及修改確認 → (04) 開展工程,項目經理全程跟進進度。每一步完成才進入下一步。

Five steps: (00) you share basic details of the space; (01) first meeting with initial floor-plan advice; (02) professional on-site measurement; (03) 3D design, revisions and approval; (04) construction begins, with a project manager tracking progress throughout. We only move on once each step is signed off.

我點樣知道工程進度?

How do I track progress on my project?

每個項目有專屬項目經理跟進,提供進度時間表、定期現場相片及巡查報告。你可隨時透過電話或 WhatsApp 查詢,所有重要決定一律書面確認,避免口頭誤會。

Every project has a dedicated project manager who provides a programme schedule, regular site photos and inspection reports. You can check in anytime by phone or WhatsApp, and every key decision is confirmed in writing to avoid misunderstandings.

會唔會中途加價?

Will the price increase halfway through the project?

圖則確認及簽約後,報價即為合約價,我們不會單方面加價。只有在你主動改動(加項目、升級物料)時,才會另出「更改工程單」(Variation Order),並先報價、先書面確認、後施工。

Once drawings are approved and the contract is signed, the quotation becomes the contract price and we do not raise it unilaterally. Additional costs arise only from client-requested changes — extra items or upgraded finishes — which are issued as a Variation Order: quoted first, confirmed in writing, then built.

可唔可以淨做設計,唔做工程?

Can I hire you for design only, without construction?

可以。純設計服務交付平面圖、3D 效果圖、施工圖及物料規格,你可自行聘用承建商。我們亦可加配工程監督服務,確保施工不偏離設計原意。

Yes. Our design-only service delivers floor plans, 3D visuals, construction drawings and material specifications, so you can appoint your own contractor. We can also add site supervision to make sure the build stays true to the design intent.

有冇保養期?幾耐?

Do you offer a warranty, and for how long?

有。工程完成後提供12 個月保養期,期間非人為損壞的施工問題免費跟進;訂製傢俬另有廠方保養。保養範圍及年期會列明在合約內。

​

Projects come with a 12-month defects liability period covering workmanship issues that are not caused by misuse; bespoke furniture carries a separate factory warranty. The exact scope and duration are stated in the contract.

21 Renovation Secrets | Hong Kong Interior Design FAQ 

裝修 FAQ|客人最想知嘅 21 個問題一次答晒

​

A. 錢​

​

Q1. 裝修要幾錢?

冇標準價,只有標準做法。要對方分項報價(拆、水電、泥水、木工、油漆逐項列),冇分項,就冇得比較。好多時都要睇設計,冇設計都係冇得比較哦。

​

Q2. 報價單點解可以差一大截?

通常係三樣嘢:計漏項、用料等級、工藝做法。平嗰份多數係少計咗,唔係慳咗。 比較前,先對齊:同一張圖、同一份物料表、同一個施工範圍。

 

Q3. 點先唔會超支?

三招:圖則定稿才開工;期間所有改動書面報價才做;預留 10–15% 備用金 ([確認])。

超支九成唔係因為貴,係因為改。

​

Q4. 付款點分期?

按進度分三期或以上,尾數一定要留(建議 5–10% ([確認]))。

​

B. 時間與工序

​

Q5. 要幾耐?

視乎面積同改動程度,一般單位約 6–12 星期 ([確認後計])。真正拖期的通常唔係師傅慢,係等材料、等決定。 所以:物料早落單,決定早拍板。

​

Q6. 正確工序係點?

設計定稿 → 清拆 → 水電 → 泥水 → 防水 → 木工/訂造傢俬 → 油漆 → 清潔 → 執修 → 驗收。 次序一亂,就要拆過。

​

Q7. 邊啲牆唔拆得?

主力牆、橫樑、外牆、防火門、公共渠位 —— 全部唔掂得。 想拆牆,先查大廈圖則,必要時入則。唔好信「師傅話得」,出事係業主上身。

​

Q8. 要唔要入則?

涉及結構、渠務改動、消防、外牆,多數要。小型工程(如更換潔具、重鋪地板)一般唔使。 最穩陣問:管理處 + 認可專業人士。

​

C. 現場與品質

​

Q9. 洗手間點做防水?

至少兩層防水 + 試水 24–48 小時 ([確認]),試完先鋪磚。 漏水九成唔係防水料差,係收口位冇做 —— 去水位、牆腳、門檻。

​

Q10. 點揀物料?

唔好淨睇樣板靚唔靚,要問三條:耐唔耐潮? 耐唔耐曬? 用幾年之後會點? 香港潮濕,木板、金屬、石材嘅表現可以差好遠。

​

Q11. 點解要出施工圖、排磚圖? 好重要 !!!! 

圖係用嚟對數同收口,唔係用嚟靚。出咗圖再改,圖就要更新 —— 唔係張圖冇用,係改咗冇 update。 冇圖,現場就靠估;靠估,就一定有誤差。

​

Q12. 驗收要 check 乜?

帶清單逐項行一次:門開關順唔順、櫃門齊唔齊、水電著唔著、去水通唔通、收口靚唔靚、有冇崩花同色差。 執修清單要白紙黑字 + 寫明期限,唔好口頭講。

​

Q13. 保養期幾長?

一般 12 個月 ([確認]),防水、水電類可另行訂明。問清楚保養由邊個負(公司定判頭),寫落合約。

​

Q14. 執修拖拖拉拉點算? 唯一方法:合約訂明執修期限,並同尾數掛勾。 冇尾數在手,就冇人急。

​

D. 設計與傢俬

​

Q15. 訂造傢俬定買現成好?

位要用到盡、要收口靚、要用十年 → 訂造。趕時間、預算緊、日後會搬 → 現成。 香港樓細、樓底矮、儲物位爭崩頭,多數情況訂造贏。

​

Q16. 樓底矮可以點做?

唔好做厚天花、唔好做層層疊嘅燈槽;收納向上發展到頂,燈光用暗藏或薄身燈。 矮樓底最忌「加一層」。

​

Q17. 設計師同裝修公司,搵邊個?

兩者都要識現場。淨識畫圖、冇落地盤經驗,圖畫到幾靚都好,現場一樣出事。

識設計、識裝修、識美感、識落地 —— 四樣都要。

​

D. 油漆: 

​

Q18. 要油幾多層?

一般:一層底漆 + 兩層面漆  。

深色、遮蓋力弱嘅色,要加多一層。 慳一層,日後色差同遮唔到底,代價更大。

​

Q19. 底漆係咪一定要?

係。底漆做三件事:封底、抗鹼、提升附著力。新灰、新水泥牆更加唔可以慳。 冇底漆 = 面漆俾牆吸咗 = 色澤唔勻、易甩。

​

Q20. 舊牆有裂痕,直接油得唔得?

唔得。裂痕要開 V 坑 → 填補 → 貼防裂帶 → 批灰 → 磨平 → 底漆 → 面漆。 直接油上去,裂痕三個月後照樣現形。

​

Q21. 點驗收油漆?

驗油漆睇三樣:一、側光睇平整度: 自然光或現場燈掠過牆身 。二、遠睇對色——退開 2–3 米睇全幅牆,檢查色差、接痕、補口、光度唔勻。三、近睇收口——行近 30–50cm 睇天花線,收口要直要貼。

Contact

Like what you see? Get in touch to learn more.

  • Facebook
  • Twitter
  • LinkedIn
  • Instagram

Thanks for submitting!

Thanks for submitting!

GET IN TOUCH:

CONTACT US:

Style50s Interior Design

Austin Tower, No. 22-26 Austin Road, Kowloon, TST, Hong Kong

​

珠海市香洲区九洲大道西2021号

中海富华里B座15楼08室

  • Facebook
  • Instagram
  • Youtube
bottom of page